NYC Halts Office Conversion at 222 Broadway
NYC halts office conversion at 222 Broadway due to safety concerns, including cracks in concrete beams, during the renovation process.

New York City building officials have issued a stop-work order at 222 Broadway, halting the office-to-residential conversion of the 32-story tower. The shutdown comes after city inspectors discovered that the project’s contractor, Leeding Builders Group, and the engineering firm, DeSimone Consulting Engineers, failed to report cracks that had developed in two concrete beams on the building’s newly added top floor.
Reporters noted that the cracks on the 32nd floor initially appeared in March and were promptly repaired, according to a GFP Real Estate spokesman. However, the developer declined to comment on whether the added weight from the new rooftop features contributed to the beam cracks.
The contractor and the engineers decided the damage was minor and did not report it to the city. A disagreement over when the damage should have been reported, not safety issues, is the only reason for the project’s shutdown, according to GFP. The building is stable, they said.
GFP Real Estate expects to complete the project within the next year, with apartment leasing already underway. The Department of Buildings is currently reviewing engineering reports for 222 Broadway and will not lift the halt until safety is assured, it said.
The enforcement at 222 Broadway is part of a broader inspection blitz by the Department of Buildings, triggered earlier this month with a potential partial collapse at another massive office-to-apartment conversion at the former Pfizer headquarters in Midtown. On July 7, two steel columns collapsed in the Metroloft’s 37-story tower at 235 East 42nd Street.
A week later, the city sent building safety inspectors across five boroughs to conduct safety reviews of unidentified construction sites. The Department of Buildings is taking a proactive approach to ensure the safety of construction sites across the city, particularly in areas with high costs and large-scale projects.
According to the agency, the inspection blitz is a precautionary measure to identify potential safety hazards. They are working closely with developers and contractors to ensure that all construction sites are safe and compliant with building codes.
In the middle of this construction boom, the city is taking a closer look at the safety of these large-scale projects. With the Pfizer building debacle still fresh in mind, the city is taking steps to prevent similar incidents from happening in the future.
The project’s shutdown.
The Department of Buildings will continue to review engineering reports for 222 Broadway and work with GFP Real Estate to ensure that the project meets all safety standards. Its goal is to ensure that the building is safe for occupants and that the construction process is completed without any major incidents, and they will achieve this by closely monitoring the site and addressing any potential issues promptly.